Untitled case file
Transcription
ESTIMATE No. ______________
M.P. No. ______________
Estimate of the expense necessary to be incurred for a bridge over the Kablu
Gully on the Akuse - Pong Road at "C".
chargeable to Vote for __________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
SUMMARY.
| Rate. | £ | s. | d. | |||
| Shelter Hut for Foreman &c | 5 | " | " | |||
| 23. | Cube yds | Excavation to piers | 1/6 | 1 | 14 | 6 |
| 155 1/2 | do | Digging and filling to banks | 2/- | 15 | 11 | " |
| 23 1/2 | do | Concrete in piers | 40/- | 47 | ||
| 52 | lin. feet | Girders Odoom | 5/- | 13 | ||
| Labour fixing do | 15 | " | ||||
| 115 | pieces | Planking to floor 7'.0" 6" 3" laid |
with open joints odoom \ | 3/- | 17 | 5 | |
| Labour laying do | 1 | 18 | " | |||
| 413 | lin. feet | Handrail plain rough 4"x 3" odoom | 5d | 4 | 8 | 9 |
| 300 | do | Odoom Boards 12" 1" for concrete |
boxes, mixing c \ | 3d | 3 | 15 | " |
| Labour making do | 1 | 5 | " | |||
| Iron Bolts for boxes | 10 | " | ||||
| 1/2 | Cwt | 4" Nails | 8 | " | ||
| Tar | 12 | |||||
| Transport do | 15 | " | ||||
| do tools by land | 2 | " | ||||
| 20 | Casks | do cement | 14/- | 14 | ||
| Carried forward | £ | 129 | 15 | 3 |
S.S.C. - (1,000)--11/4/'02.
(Public Works Form, No. 5.)
Typed from the scan. Spellings follow the original and may contain mistakes.