Scanned page 201 of SNA-49: Untitled case file
Scan PTDC0203.JPG · open full size

Transcription

ESTIMATE No. \\\\\\\\ (132)

-:o:-

M.P. No. \\\\\\\\
ESTIMATE of the expense necessary to be incurred for a Bridge over the
Dornive Gully, Akuse - Pono Road (at D)

chargeable to Vote for \\\\\\\\

SUMMARY.

Rate.£s.d.
Shelter Hut for tools and Foreman }5""
27Cu. yardsExcavation to piers1/62"6
130do.Digging and filling to banks2/-13""
39doConcrete in piers40/-78""
82Cube feetGirders; odoom5/-2010"
Labour fixing do"15"
194piecesPlanking to floor 7'.0" x 6" x 3"3/-292"
Labour laying do25"
308Lin. feetHandrail 4"x3" rough odoom5.d684
300doOdoom Boards 12"x1" for concrete boxes3.d315"
Labour making do15"
Iron Bolts for boxes"10"
1/4Cwt4" Nails"8"
Tar"12"
Transport do"12"
33Casksdo cement14/-232"
do tools by land2""
Carried forward£189410

S.S.C. -(1,000)-11/4/92.