Untitled case file
Transcription
2980/00.
Colonial Secretary Office.
Accra.
28th October, 1907.
Sir,
With rfrence to your letter No.P.17/L1/07, dated the 23rd ultimo, i am directed by the Acting Governor to reply to the enquiries as follows:—
1. The Saltpond nsuasem road and bridges have been repaired and are in good order as far as NYAMEN, distance of about 12 miles — The construction of steel and concrete brides will he commened in January, 1903.
2 The plans and specifications are now being prepared by the Consulting Engineers; but that no date can, at present, be given for the commencement of this breakwater,
3. Action has, for the present, been deferred provisional until the permanent bridges on the Cape Coast -Prahsue, and Saltpond-Nsuaem road have been completed.
I am ,
Sir,
Your obedient Servant,
(Sd) C. Riby willaims,
ACTING COLONIAL SECRETARY.
THE ACTING COMMISSIONER,
CENTRAL PROVINCE,
CAPE COAST.
Typed from the scan. Spellings follow the original and may contain mistakes.